8 MW of prime power for LNG and helium plant in South Africa

Plant is first helium facility in Sub-Saharan Africa

Himoinsa Southern Africa has supplied rental equipment with 8 MW of prime power for a liquefied natural gas (LNG) and helium plant in Virginia, Free State, South Africa.

Helium is required worldwide to manufacture semiconductors, and fiber optic cabling and provides deep cryogenic cooling for the superconducting magnets that are critical components in magnetic resonance imaging (MRI) devices.

The project has required the installation of eight fully synchronized generator sets, neutral earth transformers, fuel tanks and a control room to run the site. A 200kVA unit was also provided for temporary use during the construction phase.

Equipment supplied includes:

  • 4 x HRYW1275 Yanmar engines
  • 4x HRMW1270 MTU engines
  • 1 x HRFW200 Iveco engine
  • 2 x 33 000 L Fuel Tank
  • 2 x TRANSFORMERS 400V/11kv 11kV

Renergen’s wholly owned subsidiary, Tetra4, is the holder of South Africa’s first onshore petroleum production right. Tetra4’s Virginia Gas Project is situated in the Free State of South Africa. The project will produce LNG (liquified natural gas) and liquid helium.

Himoinsa Southern Africa has supplied rental equipment with 8 MW of prime power for an LNG and helium plant, required worldwide to manufacture semi-conductors, fibre optic cabling and provides deep cryogenic cooling for the superconducting magnets that are critical components in magnetic resonance imaging (MRI) devices. (Image: Himoinsa)

The plant is Sub-Saharan Africa’s first helium facility, making South Africa one of only eight countries globally to produce and export liquid helium and South Africa’s first onshore LNG operation.

During the construction process, no electrical connection was available, necessitating Renergen to proceed with a self-build electrical connection to the Eskom grid infrastructure and, in the interim, ensure they had a temporary, prime power solution to ensure timely commissioning of the Phase 1 Virginia gas Project.

Local utility Eskom would not be able to provide the dedicated power supply required to the site for a minimum of eight months. The Himoinsa team installed and commissioned a fully functioning power plant within three weeks of the site being ready.

Eight, fully synchronized generator sets, neutral earth transformers, fuel tanks and a control room, were installed to run the site at 8 MW Prime capability, compliant with all health and safety requirements. A 200kVA unit was also provided for temporary use during the construction phase.

As the massive compressors used for the manufacturing process have large step-loads, it was vital to ensure these did not cause power tripping which would interrupt production capability. The 8 MW, 11kv voltage solution ensured sufficient power redundancy.

POWER SOURCING GUIDE

The trusted reference and buyer’s guide for 83 years

The original “desktop search engine,” guiding nearly 10,000 users in more than 90 countries it is the primary reference for specifications and details on all the components that go into engine systems.

Visit Now

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Becky Schultz Vice President of Content Tel: +1 480 408 9774 E-mail: [email protected]
Julian Buckley Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Chad Elmore Managing Editor E-mail: [email protected]
Tony Radke Vice President of Sales Tel: +1 480 478 6302 E-mail: [email protected]
Roberta Prandi Power Progress International Brand Manager Tel: +39 334 6538183 E-mail: [email protected]