907 MW Mexico Power Plant Starts Commercial Operation

16 June 2020

GE said that Techint’s Norte III combined cycle power plant in Mexico has achieved the start of commercial operation using four GE 7F.04 gas turbines paired with four GE H33 generators and two steam turbines from Toshiba.

GE to operate, maintain facility

Under the terms of the agreement signed in 2018, GE will also operate and maintain the 907 MW plant, located in the municipality of Ciudad Juárez, in the state of Chihuahua, Mexico, for the next 25 years.

“We chose GE to collaborate with us on the Norte III plant because of its reliable technology and total plant-service solutions,” said Alejandro Maluf, CEO Techint North America. “We believe this important project will allow the consortium to leverage our collective global expertise in infrastructure, energy and project financing to support the expected growth in the Chihuahua region as was identified in the PRODESEN 2017-2030 plan.”

At the start of 2015, Mexico’s Federal Electricity Commission (CFE) commissioned the development of a combined cycle power plant just south of Ciudad Juarez in the State of Chihuahua, Mexico, to help meet the growing need for electricity in the region. The Chihuahua region was identified in the 15-year infrastructure development program for the enhancement of Mexico’s national electric system–PRODESEN 2017-2030—as a “deficient node,” given its expected growth in the next decade. The Norte III combined cycle plant will help to support this growth.

“We are proud that our gas turbine technology and total plant solutions including O&M services will help meet the growing electricity demand in Mexico, while offering capacity and efficiency guarantees tailored to meet Techint’s needs,” said Eric Gray, Vice President for Americas region, GE Gas Power. “The project was performed with the highest standards of quality and safety in crucial collaboration with FieldCore, the field services execution team owned by GE, providing productive and reliable results for our customers including Techint.”

As part of the 25-year operations agreement, GE will provide a full spectrum of digital solutions, including GE’s Asset Performance Management and Operations Optimization solutions to help predict and reduce unplanned downtime and improve power plant productivity. GE’s software will provide direct support to the GE O&M team in achieving the guaranteed capacity outcome.

GE has its third largest 7F gas turbine installed base in the world in Mexico, where GE began its operations in 1896. GE’s 16,000-square-meter Morelia Service Center, located in Morelia, Michoacán, Mexico, provides maintenance, testing and repair solutions for the Latin American region.

Celebrating 30 years

June marks the 30-year anniversary of GE’s 7F gas turbine technology. GE’s first 7F started commercial operation in 1990 and is still generating power today. The 7F technology is core to GE’s Gas Power portfolio of full life cycle products and services. Its installed base of 950+ units (including 96 in Latin America) generates 150 GW daily.

 

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

POWER SOURCING GUIDE

The trusted reference and buyer’s guide for 83 years

The original “desktop search engine,” guiding nearly 10,000 users in more than 90 countries it is the primary reference for specifications and details on all the components that go into engine systems.

Visit Now

CONNECT WITH THE TEAM
Becky Schultz Vice President of Content Tel: +1 480 408 9774 E-mail: [email protected]
Julian Buckley Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Chad Elmore Managing Editor Tel: +1 262 754 4114 E-mail: [email protected]
Josh Kunz Power Progress Brand Manager Tel: +1 414 379 2672 E-mail: [email protected]
Roberta Prandi Power Progress International Brand Manager Tel: +39 334 6538183 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA