Data centres fuel continued Aggreko growth
16 November 2026
Data centre projects represented 31% of Aggreko’s revenues in the US during the first nine months of 2026, the company has reported in its latest financial results.
US revenue grew by 48% in the period year-on-year, representing an additional US$279 million in data centre projects.
Over the same nine months, data centre projects represented 17% of revenues in Europe and 8% in Africa, the Middle East and Asia.
Gas generators in Aggreko’s global fleet. (Image: Aggreko)
US IPO update
The company said it its results announcement on 10 November that the planned IPO in the US is still going ahead, but with the timing, number of shares and the price range still to be determined.
An amended F-1 filing relating to the proposed IPO has been posted of the US Securities and Exchange Commission (SEC) website, reflecting the most recent financial results.
Total revenues for the nine months were $3.16 billion, up 31% year-on-year. Excluding acquisitions, revenues were 28% up. EBITDA increased by 22% to $1.10 billion.
The power renter said its performance had been particularly strong in its Americas and European businesses.
During the period the company invested $759 million in its fleet, of which a remarkable 73% represented growth CapEx.