Modularity speeds delivery for data centers
17 November 2026
Modular power blocks can help speed delivery times while shifting the industry toward capacity purchasing
During a presentation on modular data centers and modular power at the EGSA Fall Conference 2026, Amy Serpliss, data center solutions architect, Schneider Electric Federal, pointed out that AI power demand is projected to expand 4x by 2028, with inference applications for AI workloads expected to grow by 150%. But many existing data centers today – particularly in the federal space in which she works – aren’t set up to handle the demand.
“What we’re seeing, especially in the federal space, is that many of the data centers today are past their lifecycle. Many of the facilities are just not ready for the AI compute workload that’s coming,” she said. “This is a significant concern because now we’re talking about edge applications, not just the large facilities.”
Physical infrastructure has become the bottleneck, Serpliss stated. Competition for skilled labor and the materials needed to upgrade existing facilities adds to the challenge.
“This is becoming a massive concern within the federal space, and for many of our commercial customers, as well, who don’t have that larger buying power or the ability to capacity purchase,” she continued. “This is where… modular becomes a very unique way to help customers get to that place where they have a capacity purchasing-like ability.”
Building on established architecture
Schneider Electric has been building modular facilities for over 25 years, by taking a generator, ATS (automatic transfer switch) and controls and integrating them into modular power blocks that can then be repeated.
“I’m not building a data center and that entire critical electrical bus and all of the distributed energy resources tied to it in a bespoke manner every time. What I’m going to start doing is working towards a tested and validated and documented architecture that we then just continue to repeat,” Serpliss explained.
“No longer are you setting up and saying, ‘Okay, we hope all the engineering was right. Let’s head into commissioning. Fingers crossed, everything’s great.’ Now what we’re doing is we’re building it in a modular format.”
This allows for more predictable performance and increased machine resilience. “If you don’t have to plan for a specific site and then move and plan for another specific site – you’re just doing the same thing over – it allows you within the industry to perfect what you’re doing in order to really provide the best possible outcome for your customers,” Serpliss pointed out.
Another benefit of modularity is reduced training time. This is particularly important in military applications, where staff deployments have a limited duration.
“Imagine what it could look like if you are in more of a modular application where you’re repeating the design over and over,” Serpliss pondered. “That particular airman that was in one location moves to another – and it can be across the world – but what they’re walking into is the same data center, the same look, the same feel. You’ve just reduced… a massive amount of your human error [from having] to learn this new system. You’ve reduced that time for them to get in and start affecting change and being [productive].”
Capacity purchasing
A modular solution can help “unlock an unprecedented speed and scale in data center expansion,” said Serpliss, moving the industry toward a capacity purchasing mindset.
“As I look at many of the larger commercial applications for data centers, they’re buying in chunks. They’re buying in years of capacity right now, and they’re buying the same thing to be repeated over and over,” she noted. “Capacity purchasing is such a foreign concept [for developers], but to remain relevant in our marketplace today, that’s really what we need from them. And one of the ways to do that is to start looking at modular.”
A modular solution may not meet 100% of their needs for a particular project, but the reward can be worth the risk in terms of speed to completion.
“If you can start to work with your customers to create more of a standardized design that can meet... 90% of their need with this particular modular design, then we can deliver it two times faster than if we do something that meets 100% of their need,” said Serpliss.
The individual orders may be smaller, but the value to the supplier adds up over time. “You may not be seeing it in a single $3 billion order,” Serpliss acknowledged. “But you’re seeing it in the smaller application where it’s the same order over and over again, which will end up at maybe a billion dollars or something along those lines.”
Baby steps
Capacity purchasing in data center development is achievable, but as Serpliss pointed out, “Many times there needs to be baby steps to get that procurement vehicle in place. Using modern modular solutions and these tested, validated designs are really your best bet in order to start creating programmatic standardization that then can turn into that contracting culture and reform that really does need to happen in order to maintain the relevancy within our marketplace today.”
This is true whether you’re working in the federal sector or the commercial marketplace.
“Today, with the customers that we’re working with, the technology and the pace is just moving quicker and quicker,” said Serpliss. “As that critical infrastructure piece that they have to build on, we need to be looking at how we can do things faster, how we can do things better or different in a way that really helps them address that.”