MAN commissions 200 MW Cambodian power plant

Premium Content

Plant needed for power security, company says

MAN Energy Solutions has commissioned a 200 MW power plant near the Cambodian capital of Phnom Penh and handed it over to the national utility, Electricité du Cambodge.

The power plant consists of 11 MAN 18V51/60DF engines and covers the average energy requirements for around 70 000 households. China National Heavy Machinery Corporation (CHMC) was responsible for the engineering, procurement, and construction (EPC) of the power plant, while MAN Energy Solutions took care of the supply and commissioning of the engines and related plant auxiliaries.

In the dry seasons of recent years, the country’s national grid has faced stability issues due to the inability of its hydropower plants to operate at full capacity, MAN said. As a result, the Cambodian government launched an emergency program in 2019 to stabilize the supply system through flexible generation capacity.

The Cambodian power plant consists of 11 MAN 18V51/60DF engines.

The project followed a tight timeline to deliver and successfully commission all eleven engines in less than 20 months. Ultimately, the MAN project team succeeded despite the numerous constraints posed by the COVID-19 pandemic.

“For three months in the spring of 2020, our supervisors were only able to monitor the assembly of the plant remotely,” said Martin Höhler, Head of Power, Asia Pacific Region at MAN Energy Solutions. “However, thanks to digital tools, a special effort by all sides and our excellent cooperation with CHMC, we were able to make up this time and maintain the ambitious schedule.”

The power plant will initially run on heavy fuel oil, however, it will be possible to operate the dual-fuel engines with much-lower-emission natural gas in the future, MAN said.

“The plant is located directly on the banks of the Mekong River in the Lvea Aem district in Kandal Province, with the potential to add an LNG terminal at a later date,” Höhler said. “Our engines are designed for natural gas and can switch seamlessly from one fuel type to another during operation.”

MAN Energy Solutions will continue to support the project after commissioning. As part of a service contract, MAN PrimeServ, the company’s after-sales brand, will supply OEM spare parts, special services and digital solutions for the power plant over the next five years. Cambodian O&M company, SchneiTec Co. Ltd., is responsible for operating the facility.

Power Progress Networking Forum

The Tariff Report Everyone Will Want...

All Power Progress Networking Forum attendees will receive access to the updated digital report by Off-Highway Research, 'The Impact of U.S. Tariffs on the Construction Equipment Industry.'

Register your interest
POWER SOURCING GUIDE

The trusted reference and buyer’s guide for 83 years

The original “desktop search engine,” guiding nearly 10,000 users in more than 90 countries it is the primary reference for specifications and details on all the components that go into engine systems.

Visit Now

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

Latest News
Successful demo for industry-first E-Stop safety system
Develon plans to launch the DX230LC-9 in Europe next January with the smart E-Stop safety system installed
Himoinsa opens Chilean subsidiary
Himoinsa has opened a business in Chile as part of an international expansion strategy
Perkins launches diagnostics app on Trackunit connected-equipment platform
UK-based engine manufacturing is joing Trackunit’s Marketplace platform
CONNECT WITH THE TEAM
Becky Schultz Vice President of Content Tel: +1 480 408 9774 E-mail: becky.schultz@khl.com
Julian Buckley Editor Tel: +44 (0) 1892 784088 E-mail: julian.buckley@khl.com
Chad Elmore Managing Editor E-mail: chad.elmore@khl.com
Tony Radke Vice President of Sales Tel: +1 602 721 6049 E-mail: tony.radke@khl.com
CONNECT WITH SOCIAL MEDIA